Do stairs go in before flooring?

When Should a Staircase Be Installed During the Construction or Remodeling Process?

Summary

In most cases, a staircase is one of the final elements to be installed in a home, typically after walls are finished and flooring is laid on the lower level. This sequencing minimizes the risk of damage to the staircase during other construction activities and allows for precise fitting and finishing work.

Detailed Explanation

The installation timing of a staircase depends on several factors, including the type of staircase, the overall construction schedule, and specific site conditions. However, the general rule of thumb is to install the staircase towards the end of the project.

Reasons for Late Installation

  • Protection from Damage: Staircases, especially finished ones with intricate details, are susceptible to damage from other construction activities like painting, drywall installation, or the movement of heavy equipment. Installing them late minimizes this risk.
  • Accurate Fitting: The final dimensions of a space can slightly change during construction due to settling or minor adjustments. Installing the staircase later ensures a precise fit and avoids the need for rework.
  • Floor Installation: It’s generally easier to install flooring around an existing staircase than to try to fit a staircase into an already floored space.
  • Safety: An unfinished staircase can pose a safety hazard during construction. Installing it later reduces the risk of accidents.

Exceptions and Special Considerations

  • Temporary Staircases: During construction, a temporary staircase might be needed to provide access to upper levels. This is typically removed before the final staircase is installed.
  • Pre-assembled Staircases: Some staircases, especially modular or pre-assembled ones, might be installed earlier in the process, depending on the manufacturer’s recommendations and site-specific conditions.
  • Complex Staircases: Staircases with intricate designs or unique features might require earlier installation to allow for proper integration with other building elements.

Building Codes and Regulations

Local building codes and regulations also play a role in determining when a staircase can be installed. These codes typically address issues such as:

  • Staircase dimensions and specifications: Rise and run, headroom clearance, handrail requirements, etc.
  • Fire safety: Egress requirements, fire-rated construction, etc.
  • Accessibility: Requirements for individuals with disabilities.

Construction Sequencing

The typical sequence of events related to staircase installation is as follows:

  1. Framing: The rough framing for the staircase opening and any supporting structures is completed.
  2. Rough Electrical and Plumbing: Any electrical wiring or plumbing lines that need to pass through the staircase area are installed.
  3. Insulation and Drywall: Walls surrounding the staircase are insulated and finished with drywall.
  4. Flooring Installation: Flooring is installed on the lower level, up to the edge of the staircase opening.
  5. Staircase Installation: The final staircase is installed, including any railings, balusters, and trim.
  6. Finishing Touches: Painting, staining, or other finishing work is completed on the staircase and surrounding areas.

Conclusion

While there might be exceptions depending on the specific circumstances, the general practice is to install a staircase towards the end of the construction or remodeling process. This helps to protect the staircase from damage, ensures a precise fit, and facilitates the installation of flooring and other finishing elements. It’s always recommended to consult with a qualified contractor or architect to determine the optimal timing for staircase installation in your specific project.